Mumbai: Mulund Dumping Ground Closure Faces Delay; BMC Sets Target To Process 15,000 Tonnes Of Waste Daily By June 2025
Mumbai: The civic officials has expressed concern over the slow progress at the Mulund dumping ground, where only 50% of the 70 lakh tonnes of waste has been processed so far. With just six months remaining to meet the target by June 2025, the contractor has been warned to ramp up efforts and process 15,000 … Read more